Who This Checklist Is For

This is for procurement teams coordinating chemical process equipment sourcing where the unit is configured, not catalog-off-the-shelf. Reactors, shell-and-tube heat exchangers, centrifugal pumps, storage vessels, mixing systems. If you're ordering standard fittings or simple valves, most of this won't apply—your supplier's catalog handles it.

I coordinate procurement for our plant—roughly $2.4 million a year across 11 vendors, and I report to both operations and finance. When I took over purchasing in 2020, I assumed sourcing equipment worked like sourcing office supplies: get three quotes, pick the cheapest one that meets spec. That assumption cost us a six-week delay and a $9,400 rework invoice on a pump skid. This checklist is the one I use now.

Seven steps. In order. Each has a checkpoint before you move on.

Step 1: Write an Operating Requirements Sheet Before You Email Anyone

The single biggest cause of bad quotations isn't a bad supplier. It's a vague request. If you send a chemical process equipment manufacturer an email that says "we need a 500-gallon reactor," you will get back a quote for something. It will look attractive. It will probably be wrong.

Before you contact anyone, write down:

  • What goes in and what comes out (chemistry, flow rate, phase)
  • Operating temperature and pressure ranges, plus upset conditions
  • Materials of construction for wetted parts
  • Footprint and utility connections available at the install site
  • Turnover rates and cleaning requirements

This document is not an engineering spec. It's a buying brief. Your process engineer will refine it later—but the brief prevents the supplier from quoting based on assumptions.

Checkpoint: Can a fabricator read this and know whether their standard skid will fit? If not, keep editing.

Step 2: Decide Whether Design and Manufacturing Are One Vendor or Two

Most buyers assume chemical process equipment design and fabrication are handled by the same company. Sometimes they are. Frequently they're not. Design houses produce P&IDs and mechanical drawings; fabrication shops build to those drawings. If you blend the two into one RFP without knowing, you get quotes at different scope levels and you can't compare them.

Ask each candidate directly: "Are you designing this, or fabricating to someone else's drawing? Who stamps the final drawings?" The answer changes how responsible that supplier is for code compliance.

Checkpoint: You can name the party responsible for the drawing set and the party responsible for fabrication. If they're different, you need both under contract—or one prime contractor who owns the other.

Step 3: Verify the Fabricator's Certifications Against Your Process, Not in General

Here's a pattern I see when buyers compare manufacturers: they assume the premium fabricator charges more because quality costs money. That's backwards. Fabricators that consistently deliver code-compliant work charge more because they've stopped absorbing rework costs. Their pricing reflects fewer callbacks, not extra markup. The causation runs the other way.

Certifications to look for depend on your equipment:

  • Pressure vessels: ASME Boiler & Pressure Vessel Code, Section VIII, Division 1 (or Div. 2 for high-pressure units). Ask for the U-stamp and recent U-1A forms.
  • Centrifugal pumps: API Standard 610 if the duty is petroleum- or chemical-service. General-service pumps follow ANSI/ASME B73.1.
  • Process piping: ASME B31.3 fabrication and welding procedures.
  • All fabricators: ISO 9001 certificate, current, with the scope matching what they claim to build.

Don't just ask whether they have these. Ask for a copy. Certificates that expired eighteen months ago still live on marketing pages.

To be fair, some standard equipment genuinely is what a buyer needs—if the process is straightforward. The verification work matters most when the unit is custom.

Checkpoint: You have current documentation in hand, not just a verbal "yes."

Step 4: Get the Drawing Set Reviewed Before You Sign Anything

Approving a quote without seeing the drawing set is like approving a construction budget without a plan. Nozzle orientation, flange ratings, material certificates, drain locations—these get resolved in the drawings. If you sign the PO first, you pay for the changes later as change orders.

What to look at when the drawings arrive:

  • Dimensions match the site survey from step 1
  • Nozzle sizes and orientation match the piping you'll connect
  • Wetted materials match the brief
  • Foundation and lifting points are marked

In my opinion, this step is where the technical staff needs to be in the room. Buyers can't sign off on nozzle orientation. So bring the process or mechanical engineer into the review before the quote goes to finance.

Checkpoint: Your technical reviewer has signed off on the drawing set. Written confirmation beats a Slack message.

Step 5: Define Where the Supplier's Scope Ends and the Installer's Begins

This is the step most buyers skip. It's also the one that generates the biggest surprise invoices.

The equipment arrives on a flatbed. Somebody has to unload it, move it, set it, align it, and connect it. Who? The chemical process equipment supplier might say "we support installation." That's not the same as "we install." Support can mean a phone call or a field technician who observes while your contractor does the work.

The chemical process equipment installation scope is where the surprises live. Ask the supplier, in writing: "Does your quoted scope include rigging, setting, alignment, utility hookup, and commissioning support on-site? Yes or no on each." Then ask your installer the same list. The two answers must overlap for every line. Gaps become change orders.

Checkpoint: You have a written scope matrix that shows who does what for every install task. No shared ownership without a named lead.

Step 6: Confirm the Documentation Package Ships With the Equipment

Documentation. All of it. Before the truck leaves the fabricator.

For any code-stamped equipment, expect a documentation package that includes:

  • U-1A manufacturer's data report (for pressure vessels)
  • Material test certificates for wetted parts
  • Welding procedure specifications and procedure qualification records
  • Installation, operation, and maintenance manuals
  • P&ID and as-built drawings
  • Relief valve sizing calculations

If this package is missing, commissioning stalls. Not always because the equipment is bad—sometimes it works fine, but the inspector won't sign off without the paperwork, and you can't safely start the process. I've seen a delivery sit in the yard for five weeks waiting on a welding record that took one email to request and five weeks to ship.

Checkpoint: Your document list is agreed in the purchase order, with a named contact at the supplier for each item.

Step 7: Set Up the Acceptance Test Before Installation, Not After

Factory acceptance testing (FAT) is standard for custom equipment. Whether it happens at the fabricator's shop or on your site, the test criteria need to be written into the PO before you sign—not negotiated when the equipment is ready.

At minimum, confirm:

  • What gets tested (pressure, leak, flow, controls)
  • Who witnesses the test (you, a third party, or a report only?)
  • What the pass criteria are
  • What happens if the test fails

Even after signing with a fabricator we'd used before, I kept second-guessing. What if the lead time slipped? What if their FAT criteria didn't match what our process engineer assumed? The four weeks until acceptance testing were pretty stressful, and the doubt didn't fade until the test report came back clean.

Checkpoint: Test criteria are in the PO. Both sides have agreed on the witness process.

Common Mistakes to Avoid

These are the ones I see most often on chemical process equipment sourcing projects:

  • Comparing quotes at different scope levels. A manufacturer quoting design plus fabrication is not comparable to a fabricator quoting build-only. Normalize scope before you compare price.
  • Treating lead time as a fixed number. Rush orders cost way more than the base price suggests, because they disrupt planned workflows—not because the work is inherently harder. That distinction matters when you negotiate.
  • Assuming "compliant" means compliant with your code. A CE-marked unit meets European requirements. Whether it meets your state or local inspector's requirements is a separate question. Verify before purchase.
  • Skipping the handoff meeting. When supplier, installer, and your engineering team haven't been on the same call, someone assumes someone else has done something. That assumption shows up as a change order.

Bottom line: informed buyers ask better questions and make faster decisions. If any of the seven steps above feels like extra work, that's because you're trading an hour of prep for a week of rework. Not ideal, but workable is fine. A surprise invoice is not.